|
Healthcare Installation Tips
Team Hierarchy—Stacked to Succeed
When establishing a functional team for your HIS project, take the
time to outline the hierarchy and clearly define the roles. We
recommend a structure that covers all levels from the Executive level
down to the Team Member level. The responsibility for members
at each level should be clear.
The Executive Level is responsible for providing overall support, serving
as the Champion for the project with Administration, the internal user
community, and the external users and customers of the project. This
level usually consists of a Steering Committee, but can be a smaller
group of Executive representatives. This level sets the tone for
the project by providing stable, consistent guidance, decision making,
budget review and support, and leadership. The Executive Level
gets reports and escalation events from the Program Manager.
The
Program Level is headed by a Program Manager who drives the project,
maintains the Master Project Plan, assigns Project Managers, attends
and chairs key committee meetings, serves as the voice of the project
to various hospital areas / committees, and maintains communication
with the vendor. This position sets project standards with regard
to status collection, issue handling, risk review, and guides the Project
Managers through the various phases of the project. The Program
Manager utilizes the Project Managers as his/her key team to assign,
strategize, and carry out all the duties necessary for the project.
The Project Level consists of Project Managers who serve as the primary
oversight body of all the various sub-teams for the project. Project
Managers help assign critical Team Lead positions, maintain their teams’ project
plans, provide plan % status to the Program Manager, and control the
speed and quality of all facets of their team. These individuals
work closely with one another, monitoring issues, insuring cross team
functionality, projecting resource needs, and setting the pace for delivery
and quality of the project.
The Team Level is made of Team Leads who are responsible for insuring
that all project tasks are completed in accordance with the project
timeline. Team Leads are instrumental in determining the necessary
makeup of their teams and utilizing the project sub-plans developed
by their Project Managers, enhancing that plan to contain the detailed
tasks, so all tasks are completed on time. The Team Leads utilize
Liaisons and other committees to gather feedback, gain signoff / approval,
and oversee their applications and/or areas of responsibility to validate
they are being handled with the utmost quality. Team Leads take
direction from the Project Managers and work with other Team Leads to
insure consistency and cohesiveness within the project. Team Leads
maintain the issues for their respective areas of the project in the
project issue tracking system.
Finally, the Team Members take direction from the Team Leads and conduct
all the tasks assigned, reporting and working through issues
as they arise. Team Members must follow guidelines set forth with
regard to reporting, tailoring, approval, and all other project-related
policies and expectations. Team Members may serve on multiple
teams and must work with other Team Members to gain knowledge and assist
as needed. Your
project will be much more successful and your teams more functional
and empowered once everyone knows their roles and limits.
Vendor Selection / Management
Vendor Built System—Is It Right For You?
Anyone with an HIS has faced this question: Should we do our
own tailoring, or utilize the vendor’s “rapid build” process? Whichever
way you choose, you have much work ahead of you. If you
believe that contracting with the vendor to do the build for
you will make your job easier, you’ll want to pay attention
to this article.
Once sold as a creative solution to smaller hospitals with limited
HIS staff, vendors have started to target larger institutions. Why
would a larger organization want the vendor to tailor their system? Some
may not be able to dedicate staff to learn a new system, and
some may want to engage the vendor in the project from a responsibility
and accountability standpoint.
If you choose to contract for a vendor built system, there are
several steps that you, the hospital, can take to help your project
stay on target:
- Require the vendor’s analysts to have a minimum of
3 years hospital experience and at least 1 year with the application. You
need skilled builders who know hospital operations.
- Your project team will need to make informed decisions. Provide
them with essential training, encourage contact with other
sites, and allow time for them to learn the base system.
- For each tailoring decision, understand your options. Will
your decision impact charging, the ability to chart, or any
other interrelated function?
- Maintain a clear, concise record of all data sheets you provide
to the vendor, including date requested, date submitted, and
version control. Keep clear records of what was submitted
so you can use it during your validation and testing.
- Insist that the vendor build small subsets of each module,
then come on site to do demos. Do not submit an entire
data collection sheet before you see how a few sample items
look and function in the system. For example, ask the
vendor to build a few orderable items from each department
and demonstrate how the system functions using this subset. Only
after you are satisfied that the system works as expected with
your data, should you begin gathering and submitting the rest
of your items for building.
- Require that the vendor present Conference Room Pilots at
various stages of the Build process. By monitoring the
progress, you can make course corrections if necessary, plus
your team will become much more familiar with the product and
the impact of their decisions as a result of these presentations.
- Plan your testing early, making sure that you receive clear
documentation on how the system has been built, so your test
plans are accurate.
- Assign a dedicated project manager to oversee your project,
helping to keep your assignments on track as well as monitor
the vendor’s deliverables.
When determining if you will tailor your system or contract
with the vendor for the job, our final suggestion would be for
you to consider what your long term support plans are. At
some point, the vendor is going to leave, and you have to be
prepared to troubleshoot and tailor the system. Would you
benefit more from your staff learning these skills early in the
project or at the end?
Defining Project Success
Shortly after your project goes live, you’ll want to determine
if your activation was a success. The overall value of
a new system is measured by the sum of its parts. There
are ways to quantify “success” objectively and subjectively. Both
can be used to your advantage if done properly.
Objective measurements of your success may consist of the following:
- Average retrieval time for lab results will be reduced by
25 seconds.
- Reported patient safety issues due to medication errors will
be reduced to 1 per month.
- Application will remain available to the user community 99.98%
of the time each month.
Subjective measurements may come from the following types of
evaluations:
- The equipment in my department is fully functional, and all
PCs, printers, and other project related devices work as expected.
- Users in my department are able to access the system with
all necessary security rights.
- The training I received was adequate and we are now functioning
with appropriate knowledge of the system.
Both of these types of measurements are valid, and it is up
to your Executive Team to determine what their measurement of
success is going to be. Executive Teams typically enjoy
objective measurements – something that can be definitive. These
measurements take some upfront effort and some level of Management
Engineering to get consistent data before and after.
Project or Program Managers should also appreciate subjective
measurements. These are usually done with a Lichert scale
survey. Our suggestion is to develop ten different questions
with a 1-10 scale ranging from strongly disagree to strongly
agree. Survey each department 5-10 days post activation
and arrive at an acceptance percentage for each department as
well as the facility average. Then survey the same individuals
30-60 days after activation and compare the improvement. This
not only gives you firm proof that the perception has improved,
(which is usually attributed in some part to getting comfortable
with the system) but it also pinpoints areas of dissatisfaction.
Preparing For Your Go/No-Go Meeting
We’re all familiar with a Go/No-Go meeting – the
event whereby key personnel sit around a table and give the “okay” to
proceed to activation. This is an extremely important milestone,
and you want to make sure that everyone is truly ready. When
your people give you the thumbs up, you want to feel confident
that they are basing their answer on firsthand analysis with
total confidence that their application, team, or technical aspect
of the activation is ready to go.
Atlanticon suggests preparing a bound document well in advance
that requires that all Team Leaders and other personnel responsible
for facets of the project, sign off for their areas. Circulate
it early so there are no surprises.
Schedule a preliminary Go/No-Go meeting at least 30 days prior
to your final meeting, performing a verbal survey of everyone’s
readiness at that time. Pose the question, “If you were
expected to sign this today, could you? If not, then what do
you need to do in the next 30 days to turn it around?”
Be prepared to deal with someone who may refuse or be reluctant
to sign. Will you require that they sign with conditions? What
action will/can you take at this late stage?
Conducting these meetings in a large room with the document being
passed around to all signers gives this event the importance
that it deserves! Above all, you want to activate a system
that is SAFE for the patients. The purpose of a Go/No-Go call
is to do the right thing. If someone truly can’t be ready,
and their situation makes for a dangerous future, then you must
make the tough call.
Training Strategy — An Important Step
Honestly, I could write for days about the importance of a good
training strategy. When Atlanticon is asked to lead a training
effort, we begin with our standard 40 page strategy and adjust
it for each client. I'm not trying to impress you with the number
of pages, but I do want to make you aware that training is no
easy phase, and there are many items to address. Our training
strategy was developed by Brian Beals, one of Atlanticon’s
most senior PMs and Training Specialists, and has been utilized
and revised over the years by other senior consultants, Bruce
Dobrient, and David Kowal.
As you approach your training phase, it is best to assign a Training
Leader that is a veteran of training and who has exceptional
organizational skills. This individual is going to be responsible
for putting together the Training Strategy.
Since each hospital is vastly different, training strategy can
vary. What works for one may not work for another. Keep in mind
that the strategy document should cover all the things you intend
to do leading up to, and during training, and should be the document
that guides your training team in the development of their approach.
Here are just a few things to address in your Training Strategy
document:
- Room space and location - where will you train and how
much space will you need
- What type of training - instructor based, computer based,
etc.
- How many hours of training
- Will there need to be pre-req classes, such as Windows
awareness
- What automated tool will you use to schedule classes
- Will you be reporting no-shows to management, and what
corrective action will occur
- Will you have a system that allows the instructor to take
over the terminals
- Are you providing enough lead time for printing your class
materials
- How will physicians and their office staff be trained
- Will you provide access to the training domain after training
- Will you refresh your training domain with updates if the
system is still being built
- Will you build starter data and have to restore it after
each class
- Will there be a competency test at the end of the class
- What if someone does not attend training and/or does not
pass the competency
- How much time will you leave between the first training
class and activation
- Will you distribute the Production logins and passwords
at the completion of class
- Have you created job descriptions for trainers and targeted
the right personality
As I mentioned earlier, training is no easy task. And developing
a good Strategy Document is the key to making sure that all your
bases are covered before you embark on this critical phase of
your project. Should you wish to discuss training ideas
with one of our training experts, please contact our office and
we’ll arrange a call.
Activation Planning — Cross
the Finish Line in Style
Activations come at the end of many, many months of hard work.
There's a lot at stake and you need your activation to be well
planned.
I'm going to list a sampling of the key things Atlanticon follows
when involved in Activation Planning. Hopefully, these "top
20" will aid you in your thinking process:
- Create A Small Activation Planning Team. Include
the interface, conversion, and one or two other key team members
- select those that are self-starters and motivated - the ones
that are always thinking.
- Develop An Activation Assumptions Document. This
document is critical. It should contain all the major assumptions
upon which you will plan the activation. State the date and
time of activation, where the Command Center will be located,
how long the activation support team will be 24 x 7, when the
vendor is to arrive, what issue tracking system will be used,
where will the help desk be located. Include as many assumptions
as you can. This Assumptions document must then be blessed
by your CIO, the Executive Team, and the Vendor.
- Plan The Activation Steps. Once
you have an agreed-upon Assumptions document,
you can begin to plan the steps. Start at a high
level - make sure that you know when the conversions
will begin, when the interfaces need to queue,
when the old system is shut down, when the converted
data is complete, and when the recovery of current
patient data begins.
- Introduce Other Teams. As you start
your outline of key steps, you will slowly start to work through
any conflicts. Gradually, introduce other key team members,
such as Registration followed by Pharmacy followed by Nursing.
- Broaden The Steps. As each group
is introduced to the planning, they can start to contribute
their key steps. When will I readmit the in house patients,
when will the allergies be updated, how will I handle the inhouse
medication profiles, when should order entry on active orders
take place.
- Insure Proper Sequencing. With each
addition, you are starting to get a plan that is free of major
sequencing issues. The most serious problem that can arise
in an activation is when your steps are out of sequence - for
example, you don't want to place medication orders before the
allergies and existing meds are entered - you'll risk missing
an interaction or drug alert.
- Gaining User Satisfaction. Document the
approach you are going to use for gaining user satisfaction.
- Conduct A Dress Rehearsal. Remember, a Dress
Rehearsal is a walkthrough of your activation plan. We like to
select key elements from the activation plan and request that
the task owners come prepared to present, discuss, or demonstrate
how they will accomplish their task(s). As a group, you will
be amazed at how one member's explanation causes others to recognize
how that task may impact other tasks. You walk away from this
with a team that is much more aware of the big picture.
- Develop Orientation Packets. Prepare to
conduct meetings with all your support team, informing them
of your expectations, using these Orientation Packets.
- Identify Roles Of Your Support Team. Will
you have Roamers, a Physician Hit Team, Department Support?
- Support Schedule. Develop an easy
to read schedule of all your support. Make sure that all teams
and departments are covered.
- Managing Food. Don't forget to assign
someone to be in charge of food during the activation. Many
places don't have food available for the night crew. And be
sure to insert rules about lunch/dinner scheduling so an entire
support team doesn't disappear at the same time.
- Users’ Activation Guide. Develop
a Users’ Activation Guide - which covers details of the
activation at a Dept Managers level. Remember, many departments
don't understand what is involved beyond how they are affected.
This is your opportunity to give high level details to all
areas of the hospital. I suggest conducting a full facility
managers meeting and present this information, requiring the
managers to take the Users’ Activation Guide and communicate
it to their department.
- Change Management / Public Relations Campaign. Make
sure to develop a good Change Management and Public Relations
campaign. Be sure to cover your internal customers, physicians,
physician offices, clinics, executives, patients, and the community.
Be aware that your executive team may have strong feelings
about how a new system is announced to current patients.
- Review The Plan. Review your activation
plan repeatedly until everyone works through their roles.
- Project Signoff. Develop your Project
Signoff document. This is used at your Go/No-Go meeting.
- Strong Coordinator. Keep your Activation
plan visible and assign a Coordinator who will insure that
everyone marches in step.
- Meeting Schedules. Schedule key
meetings throughout the activation, making sure to gain input
and feedback from department liaisons, managers, vendors, and
executives.
- Issue Dashboard. Develop a useful
dashboard that can be easily maintained throughout the activation.
This dashboard should give you a quick glimpse of issue closure
and critical status.
- Hot Topics Communication. Develop
a Hot Topics news brief that goes out each day at the same
time. It should cover key information that is helpful to the
user community. By preparing a binder or special location in
each department, you can have a designated spot for all users
to retrieve this sort of communication.
Atlanticon has helped orchestrate many successful activations.
We would be happy to schedule a one or two day overview of
activation planning at your site. We have many checkoff items
that help insure your activation is as smooth as possible.
Project Phases — Avoiding
Phase Overlap
There is much to be said about Project Phases - we all know
that these are typically PLAN, DESIGN, BUILD, TEST, TRAIN, ACTIVATE.
There are many variations to these phases and each of us is free
to insert more phases to our plans if it makes sense.
Without getting into great detail about what goes into these
phases, I want to touch on something more simple - "Phase
Overlap." Have you ever been in a project where one of your
phases begins before you have finished the prior phase? Despite
your efforts to build a great project plan, unexpected things
resulted in your team not being able to stay on track. No slack
time, vendor delays in delivery, more issues than expected, or
a team member that isn't able to deliver - these are all common
events that can cause "phase overlap." Sound familiar?
There are a few things that can be done to avoid this:
- AVOID ANNOUNCING THE ACTIVATION DATE TOO EARLY.
Don't publicize your go-live date to the entire
community when you kickoff the project. Instead,
announce that you'll go live in the Summer of 2008 or the fourth
quarter of 2009. You and your executive team can
know what your target date is, but avoid announcing
an exact date until you absolutely have to.
- BUFFER and PRODUCTIVE TIME. Build
in a time buffer to each phase by budgeting people
at 32 hours of productive work per week. Don't
expect a pace of 40-50 to last very long. Priorities
change, vacations arise, roadblocks are encountered,
etc.
- DEFINE PHASE COMPLETIONS. Clearly define
what constitutes the end of each particular phase and don't
deviate from that. For example, it isn't good enough to simply
say that the DESIGN phase ends on Nov 15. You have to clarify
that the Design phase is over when 100% of all design documents
have been signed off by the user champions, and that is to
occur no later than Nov 15. Also, set mock signoff deadlines
prior to each phase completion date to pinpoint potential trouble
areas.
- PHASE CELEBRATIONS. Schedule a MILESTONE
celebration at the end of each phase - this lets your entire
team know that they have accomplished something major. No one
wants to be the one person that delays the end of a phase.
- THINK TWICE ABOUT OVERLAP. Think very
carefully before you decide to start a phase when the prior
one has not been completed. Why would anyone want to start
building when design hasn't finished? Or start testing when
building is still going on? The answer is that you don't want
to - but even the best-intentioned leaders will convince themselves
that they have no choice but to overlap phases in order to
stay on target. Don’t
fall into this trap.
I know these seem like simple suggestions, and they are. However,
many projects do get away from the best PMs. Atlanticon tries
to approach each client and each project as unique - and we
try to build in safeguards to help keep projects on track.
While nothing ever guarantees perfect success, these simple
tips can make a big difference.
Making the Project Scope Useful, not Useless
Many years ago, we noticed that most sites develop Charters
and Scopes and Implementation Visions - nicely bound and impressive
to view from a distance. But once they were written, they
collected dust and were never referenced again - certainly not
what most would consider useful project documents. The
problem was that very few people ever referenced these items,
and they were not widely shared among the stakeholders, let alone
the project team.
We also noticed that vendors would provide a Scope Document
as part of the purchase. These Scope Documents stated WHAT
you bought, but did nothing to state HOW you
would use them in your organization. Integrated systems
are highly flexible, and how you choose to use them can vary
greatly from hospital to hospital.
So, projects would march along feeling comfortable because there
was a Charter on the credenza in the CIO’s office and the
vendor had provided a Scope Document. Here’s where
the problems would begin. Part way into Design, nursing
might say that they need 25 assessments built, and Pharmacy feels
that they could benefit from 5 or 6 as well. How about
50 or 60 ordersets to go along with that? And a couple
dozen reports. After all, you did buy a report writing
utility. Your project has now encountered SCOPE CREEP,
and you are still in Design mode.
At Atlanticon, we believe in providing a Common Sense approach
to projects. Projects should not be measured by the pounds
of documents created, but rather, the ease with which your team
can carry out their duties and the quality of your finished product. In
order to aid in this, we encourage all hospitals to create a Scope
Document that explains your project, not your purchase. It
should cover:
- What you've purchased
- The primary function / purpose of each purchased item
- Who will use it
- And exactly How it will be used
You also want a Scope Document to cover ALL the new components,
such as:
- New Systems
- New Applications
- Support Tools
- Hardware
- New Interfaces
- Conversions
Finally, you want a Scope Document to be bound, approved,
and signed by all the Stakeholders before your project begins. This
keeps your project from creeping into the next 3 years.
Atlanticon believes that a proper Scope Document should address
purchased modules as follows:
- Application: Order Management
- Function: Allows the tracking of all orderable
items and provides clinicians a method for requesting items
and services electronically, generating an interface message
to outside systems and/or printing requisitions in the providing
department.
- Used By: In our project, nurses, unit clerks,
and doctors will be placing electronic orders to Radiology,
Lab, Physical Therapy, Nutrition, and Cardiology. Paper
requisitions will print in all these departments, except for
Lab and Radiology, who will each receive their orders across
an interface and generate requisitions from those departmental
systems.
- How Used: Each of the departments will perform
their duties based on these orders, with Cardiology and Physical
Therapy generating automatic charges as a result of the order. Nutrition
will generate worklists to assist them in filling trays. Radiology
and Lab will receive these orders via interface and perform
their duties, as outlined in the section specific for their
systems.
Each application, each interface, each conversion should be
similarly spelled out.
And if your plans change slightly during the Design phase, the
Scope Document should be revised and the revised section clearly
marked, following approval by your steering committee governing
scope changes.
Another example of how a Scope Document can benefit
you comes in the area of hardware. This document should state
what types of new hardware the users should expect, helping
answer the common question, "Will my printer or workstation
need to be updated or replaced?" By stating this upfront,
your technical team has a clear guideline on who gets new equipment.
A Scope Document is like a Project Plan - it's created once
and maintained / reviewed / referenced repeatedly. And
by obtaining the necessary approvals, your scope can't change
without the impact being escalated to the Executive level for
approval. Furthermore, anyone in your organization can
read and understand your project.
Keep in mind that Charters have a place—they serve as a
starting point and a vision for the project. And Scope
Documents from the vendor serve a purpose, telling you what you
have contractually purchased. However, there is not enough
detail to make it clear to everyone what the limits are. Scope
Documents are all about setting clear limits and providing definition. What
systems are involved, what departments are involved, what applications
will be used, what interfaces will be in place, what type of
equipment will be used, etc. Read your Scope Document carefully
and determine if it clearly gives you limits. And make
sure the vendor agrees to it—you don’t want to document
that you’ll register patients in 15 locations if the vendor
was of the understanding there would be 2 points of registration.
Document it, get it approved, bind it, and get all stakeholders
to sign it. The Scope Document will help keep your project
on track.
When to Boost Your Staff with Consulting Help
Many CIOs and Directors have faced an identical dilemma: “How
do I install a new HIS with my current staff so busy? And if
I choose to use consultants, how do I utilize them?”
The best answer is, "Use consulting help where you will
get the most benefit." Each site is different, and
before coming up with the right answer, you have to figure out
your most pressing needs. When it comes down to it, you have
TWO options for how to use your consulting dollars:
Option 1: Utilize consultants for their skills
and expertise in implementing projects, focusing on their knowledge
of a particular application. Bring them in to make sure your
new project stays on track and is built to allow you to make
the most of your new system.
Option 2: Use your OWN people to learn and build the new system.
Insert consultants to take over the daily support of the legacy system while
your trusted staff obtains all the new knowledge. After all, it's your staff
that will need to be the experts after activation. Don’t allow them to
get behind the 8 ball.
Assigning your staff to build a new system yet failing to free
them from day-to-day support, can cause frustrations. Some
of your staff may prefer the comfort of supporting your existing
system, occupying their time with old duties and never jump fully
into the new system. Be cautious of this. As
you plan your next project, please consider both options - Atlanticon
is very willing to help with either one.
Vendor Contracts — Keeping Control
For those of you who are about to initiate a vendor contract
for a major HIS project, your time to clarify some basic expectations
is now. In addition to the legal review required of all
contracts, you as an IT or Project person will be living with
the contract throughout the entire life cycle. You can
benefit by adding some commonly overlooked items before the contract
is final.
Once the contract is signed and your project begins, you are
locked into the terms. While each contract is vastly different,
we have some very simple tips that should be considered. By
covering these in the contract, you will have better control
as a customer:
- Experience - insert requirements into
the contract for the experience level of the vendor's analysts
- don't take junior level experts
- Scope - understand that the scope document
the vendor provides usually covers what you purchased and/or
the services the vendor is going to commit to the implementation. It
typically does not address how you intend to utilize the system. Your
RFP may not adequately cover your expectations.
- Structure - you need to determine your
internal team structure so it works in conjunction with the team
the vendor puts together. Discuss this with the vendor
and insert language that helps insure the best possible team
on both sides
- Domains - be clear in the number
of pathways, domains, or environments the vendor will commit
to build/maintain for you. Development, Training, Production,
etc., are examples. Will you need a temporary domain to
receive conversion tests?
- Build - be very wary of a process where
the vendor performs the build for you. How will you control
the outcome and how will you insure the quality, maturity, experience,
and understanding of those that build?
- Team Knowledge - insist on your team receiving
adequate training of the system capabilities prior to the decision
making phase. Otherwise, you may become your worst enemy
and make decisions without adequate knowledge.
- Iterative Build - interim build checkpoints
or conference room pilots should be put into the contract, with
the clear expectation that your system will be built in small
pieces until you are comfortable with the design. Perform
an iterative build, making sure you are confident that your
design is sound and approved by all.
- Testing - don't be shortchanged on the
timeline provided for testing, and most importantly, understand
the vendor's commitment to addressing issues between rounds of
testing. Will they provide test scripts?
- Liaisons - be prepared with your Liaison
strategy and commitment levels, and be confident in the role
they will play as subject matter experts with their vendor counterparts
- Issues - have the right issue tracking
system in place - hospitals tend to delay this. Issues
arise and commitments need to be documented, especially during
the contracting phase. Be clear who will control the tracking
of issues - avoid offers for your vendor to track your issues.
- Training - don't fail to count your training
dollars in your budget, and set clear expectations of what support
will be provided by the vendor. Will they provide a CBT? Will
they provide sample training material?
- Committees - establish the appropriate
level of committees to guide the project, such as Steering Committee,
Physician Committee, etc., including members from the vendor.
- On Site - clearly document the expectations
for vendor visits, including agenda, number of visits, duration,
schedule, and participants. Clarify that your visits should
begin by noon on Monday and end by 5 pm Thursday, or whatever
you feel is appropriate and reasonable.
- Partnership - prepare the contract in such
a way that there are incentives for both sides to work as a team
and succeed together. Be cautious of using too many penalties,
as they may backfire and cause one side to take shortcuts to
avoid them. Insert checkpoints that will support honesty
in disclosure of critical issues. It's all about the safety
of the patients - don't lose sight of that in your contract.
Project Liaisons—Gaining
Commitment
HIS projects require dedicated effort and involvement from each
and every department that will utilize the system. Most
hospitals do a fairly good job of obtaining representatives or “subject
matter experts” from the larger departments, radiology,
lab, nursing. But is it enough?
In order for a project to be most successful, every department
needs to be involved in the decisions, the design, the build,
the testing, the training, and the activation. How involved? It
depends on the complexity of the system in each area. For
example, if physical therapy will only receive electronic orders
into the new system, their involvement won’t be nearly
as much as radiology, which might have an interface to an RIS,
generate charges, post results, and insert PACS images.
In either case, all involved departments need to assign a Liaison
to the project. And it is up to the project manager to
estimate the amount of effort necessary from each. This
is tricky to do, but not impossible. The amount of time
required of a Liaison may be heavier in certain phases of the
project. The project manager should also clarify the duties
of the Liaison—how much of their committed time will be
spent in testing, design, communication, etc.
In order to solidify commitment from the department and the Liaison,
we recommend a Liaison Commitment Form—a simple agreement
between the project team and the department and Liaison which
outlines the importance and the expectations. It empowers
the Liaison to make decisions on behalf of the department and
helps secure the mindset that the project belongs to every department,
not just IT.
Atlanticon is willing to discuss this in more detail with anyone
challenged by a lack of departmental commitment.
Project Readiness—Signing
Off In Style
After many, many months of very hard work, you turn on your
new system, All goes well – patient care picks up
where it left off, new registrations start flowing, bills drop,
meds are charted, and you find yourself standing with a large
group of happy colleagues. It’s the dream of every
project manager. But if things don’t go so well,
you may find yourself standing alone. While it may not
have been your sole decision to go live, it may seem like it.
HIS projects are group efforts. They don’t belong
to IT and they don’t belong to the project manager. The
success belongs to everyone – each department, each liaison,
each analyst, each vendor rep, each director. If everyone
is willing to share in the success, they must all be willing
to share in the responsibility. We frequently see a team
divided at the first sign of a post-activation problem. But
it doesn’t have to be that way - - - provided you implement
a good Project Readiness Signoff document
Prior to go-live, your project needs to have two Go/No-Go meetings
with the result being that all involved parties sign a well drafted
Project Readiness Signoff. There are three major steps
to a successful signoff:
- You must have the appropriate people at the table to sign
their respective sections. An IT member should not sign
off for any department – the department Liaision and/or
Director should.
- The document must address each signoff area very thoroughly
and clearly. Don’t simply state that “Pharmacy
is ready for activation.” Instead, word the statement, “Pharmacy
has been thoroughly involved in all decisions made, validated
that the compendium is built properly, all meds have been tested
and can generate charges, pass to charting, and cross the interface. Pharmacy
agrees that the system is ready for activation and all Pharmacy
personnel are familiar with the system and deem it safe use.”
- Include all appropriate personnel of the project (your extended
project team, if you will) in the signoff process – those
in charge of each involved department, the interface and conversion
leader, equipment manager, help desk supervisor, training leader,
activation planning crew, finance, etc.
When your extended team signs and gives their blessing to proceed
to activation, they now have a stake in the outcome. And
in the event that something goes wrong, the “team” is
more likely to stay together and fix the problem.
The final benefit to having a quality signoff is that each person,
knowing they are expected to sign, will put a little more priority
on a review of the system prior to go-live. That extra
bit of validation may uncover some remaining bugs before activation.
Setting an Activation
Date
In the recent past, Atlanticon has consulted with many different
hospitals, all asking us to help them determine an activation
date. Setting an activation date is an extremely important
and sensitive subject.
Setting a date is important for the obvious reason—you
need a target to drive toward. But what drives the setting
of a date? Many things:
- You must shut down an existing system at a certain time due
to support or contractual dates
- A new implementation has a daily cost—the sooner the
activation, the better
- Commitments made by executive staff to the Board, the community,
or other stakeholders
- Contractual obligations with the vendor
- A rush to recognize the savings or benefits of the new system
While no one can argue the importance of setting a date, Atlanticon
cautions against publicizing it too early.
Accurately setting an activation date too early in the project
can be like trying to hit a bullseye in the dark. Large
HIS projects have enormous amounts of variables that can alter
the activation date. Unexpected team member changes, faulty
code, errors in design or build, unexpected system issues, delays
in hardware readiness, slow decision making, and interface issues
are just some of the many things that can help derail a project.
Once your executive team publishes a date to the user community,
it becomes very difficult to change that date. Changed
dates can give the perception that the project wasn’t managed
properly, the vendor wasn’t delivering successfully, or
the system isn’t safe. And the real reason may be
none of the above. But the fear that a delay will be received
incorrectly, is sometimes enough to force a project to move on
when a delay may have been in the best interest of everyone.
There is a reasonable way to approach this. We recommend
that you select a date that is driven by a complete and thoroughly
reviewed project plan. Once that date is selected, it should
not be published to anyone outside the immediate project team. The
early announcement should be general, such as, “The new
system will be ready for use in the first half of 2010.” When
is it safe to pick a date and put a stake in the ground? Atlanticon
recommends that you announce an exact date at the completion
of integration testing round 1. Only then will you have
a comfort level that design is solid, build was successful, and
the system functions as a whole. You will have
at least two more rounds to work through remaining issues, but
at least you’ll have a fairly strong comfort level with
the date you announce.
More Through Motivation
Have you ever been part of a phenomenal project team? You
feel that together you can accomplish anything. Everyone
has a “can do” attitude, each team lead takes ownership
of his/her assignments, and teammates jump in to help when a
colleague is in trouble.
While these projects leave a wonderful, lasting impression,
not all projects enjoy the same dynamics. Occasionally,
Atlanticon joins a project and we witness a lack of motivation,
team burnout, and even organizational resistance to change.
Hospital IT projects need to succeed - patient safety is at
stake. You need your project team to be stellar. Your
employees are the most valuable resources you have. Giving
them an emotional tune-up from time to time is a great investment.
When Atlanticon encounters some "not-so-stellar" team dynamics,
we recommend a pep talk. Not just any pep talk—we
encourage our clients to seek the help of a specialized speaker – one
that focuses on motivating teams and encouraging a cohesive work
relationship. The turnaround in morale and project enthusiasm
can be amazing.
Lack of motivation can account for a 15-30% drop in productivity,
and that’s an enormous cost by all counts. Enlisting
the help of a speaker for even one successful “session” can
pay for itself many times over by way of performance improvement,
and help you achieve a long lasting change in how your team views
themselves. Here are some indicators that your team might
benefit from a team building session:
- Lack of participation at team meetings and/or general non-responsiveness
- High occurrence of absences, especially when deadlines are
looming
- Complaints about too much work or responsibility
- Lack of ownership of issues or tasks
- General feeling of negativity and isolationism
- Open comments relating to failure of the project
Atlanticon exclusively utilizes one partner for this purpose,
Ms. Jane Boucher, a nationally known author and speaker on this
topic. She is the author of, “How To Love The Job
You Hate” as well as several other motivational books.
Jane is also very effective when asked to review a work team
to identify reasons for diminished performance. She effectively
takes the next step to help mediate a team to be highly effective. Next
time you notice a low morale, remember this article and consider
the benefits of repairing the team you have. People need
tune ups too!
If you think your project or organization might benefit from
such a service or would like to discuss this further, please
contact us.
Assigning Ownership
in Your Project
Have you ever learned a lesson the hard way? Those lessons
seem to stick, and I’d like to share one of my own, courtesy
of the first project I ever managed. They don’t teach this
stuff in textbooks – or if they do, they don’t
highlight it enough.
I was managing the install of a large HIS. My project plan
was in good shape, I had all the major teams created, departmental
liaisons were established, and we were rolling. We were
about to positively alter the workflow of every department in
the hospital, replacing nearly all the legacy systems. Months
into the project, the training phase was about to begin. The
training leader was now ready to review all the modified policies
and work them into her training curriculum. We had liaisons. Surely
they knew that they needed to modify their policies by this time. Well,
apparently they didn’t. One quick meeting and we
recognized that there had not been a single point of contact
from the project team assigned to ensure everyone understood
the task of “Revise policies” – and more importantly,
to ensure that they were all completed in a consistent, hospital-accepted
fashion. And who would have known that policy revisions
have to go through a committee that only meets every other month
(and just met the prior week.)
Here’s where my big lesson came in – the part that
added pain to the learning experience. Since I had failed
to assign anyone as the point person, and now everyone was too
busy to take on this task, I learned that the Project Manager
(me) gets to absorb the unassigned duties.
I spent the next two weeks of my life working way too
closely with policy details from every department, helping everyone
understand the changes that would take place and how those changes
would alter current departmental policy. Calling an emergency
meeting of the Policy Board so they could review and approve
nearly 75 new and revised policies, was not a picnic either.
We have incorporated this lesson into Atlanticon’s standard
methodology—and leave nothing to chance when it comes to
ownership. We push to make sure that there is a designated
owner for all aspects of a project. Every key file, every
set of screens, all reports, policies, finance, forms, security,
activation—all these areas need a designated coordinator
to make sure that proper attention is being given.
Atlanticon utilizes an org chart for naming leaders to all teams,
in concert with an Ownership Matrix that covers the bases for
all key files, applications, and other functions. This
results in team members that know what is expected early in the
project, it reduces the chance of someone inadvertently overwriting
your work, and gives the entire team a solid understanding of
who they need to speak with for most of the areas of a project. All
of this reduces the unnecessary traffic that a PM has to handle
and it’s just one additional approach that helps make an
Atlanticon project go more smoothly.
Simplifying Your Post Activation Audit
Shortly after your project goes live, you’ll want to determine
if your activation was a success. The overall value of
a new system is measured by the sum of its parts. There
are ways to quantify “success” objectively and subjectively. Both
can be used to your advantage if done properly.
Objective measurements of your success may consist of the following:
- Average retrieval time for lab results will be reduced by
25 seconds.
- Reported patient safety issues due to medication errors will
be reduced to 1 per month.
- Application will remain available to the user community 99.98%
of the time each month.
Subjective measurements may come from the following types of
evaluations:
- The equipment in my department is fully functional, and all
PCs, printers, and other project related
devices work as expected.
- Users in my department are able to access the system with
all necessary security rights.
- The training I received was adequate and we are now functioning
with appropriate knowledge of the system.
Both of these types of measurements are valid, and it is up
to your Executive Team to determine what their measurement of
success is going to be. Executive Teams typically enjoy
objective measurements – something that can be definitive. These
measurements take some upfront effort and some level of Management
Engineering to get consistent data before and after.
Project or Program Managers also appreciate subjective measurements,
usually done with a Lichert scale survey. Some project
teams have great intentions, but due to a lack of time or a lack
of experience, end up doing nothing in the way of a post activation
audit. Atlanticon suggests that before you opt for “nothing” at
least consider the subjective style of auditing. It’s
simple AND effective.
We suggest you develop ten different questions with a 1-10 scale. Survey
each department 5-10 days post activation and arrive at a satisfaction
score for each department, each question, and across the facility. Survey
the same individuals in each department 30-60 days later and
compare the improvement. The numbers are very powerful
and speak volumes about the success of your project.
Not only will you have quantitative numbers to boast your success,
but you will have been able to pinpoint dissatisfied areas, allowing
you to focus some much needed attention.
Tracking Issues in Your Project
Tracking project issues properly and diligently is one of the
most important things you can do for
your project. One of the first things we do when joining a project
is to assess the manner in which
issues are being tracked, and the tool that is being used to
track them.
We should define an issue first. An issue should be any outstanding
question, concern, problem, or decision that you feel needs to be tracked or documented.
Let’s face it - issues begin
mounting as soon as the system is selected. Every issue you encounter
should be logged and
tracked, reducing the chance of addressing the same item twice
- - or not at all.
Project issues belong to you, the hospital. In order to effectively
record and track them to
completion, you should avoid the following common pitfalls:
- Don’t try to make the current help desk software double
as a project issue tracking system.
- Don’t utilize the vendor’s issue system as your
only means of tracking issues.
- Don’t open the issue tracking system to too many hands.
- Don’t attempt to use a spreadsheet based software to
track issues.
- Don’t wait too long to begin tracking issues.
Atlanticon has created an Access based issue tracking system
called HITS, which stands for Hospital Issue Tracking System. It
was developed for use at all our client sites to help them alleviate
the cost of purchasing a system specifically for tracking issues. HITS
became so well utilized, that we decided to give it away to any
hospital that has an issue tracking need. It’s our
way of helping offer something to the healthcare IT community.
Here are some of our recommendations when it comes to issue
tracking systems:
- Recognize the value in documenting key decisions and resolutions
- Utilize a flexible, report-rich database system
- Plan ahead and create fields and values that make sense and
are useful
- Determine who will have access to it (we recommend team leaders
and PMs)
- Develop clear rules for logging issues, defining what your
team deems an “issue”
- Make the review of issues a standard part of your regular
team meetings
- Assign someone to oversee the quality of information being
logged
Here is a sample of the issue entry form from HITS. Feel
free to contact Atlanticon for a complimentary copy of HITS.
Implementing Ordersets – Good
Planning is the Key
When implementing an Orderset within a new HIS system, correctly
meeting the needs and wants of your physicians, nurses and other
end users is key to success. It is often very difficult to address
existing and newly requested functionality, requirements, and
regulatory compliance while at the same time reducing medical
errors and addressing many other issues and concerns. That’s
why it’s important to thoroughly work through and map out
the entire process.
Utilizing experienced resources to plan, design, build, test,
and implement the new system is vital for getting the system
up and functioning within the allotted timeframe and budget while
at the same time gaining approval from the end users. With a
resource that provides the proper experience, information, planning
and foresight, you can avoid unwanted issues and problems.
The Plan
The plan needs to include adequate communication, design, approval,
testing, and training with the appropriate clinical representatives.
The representatives should thoroughly understand the new capabilities
and limitations of the system and whether or not the new functionality
will work seamlessly with the expected workflow process. Your
plan should also include processes that accommodate new requests
and requests for revisions, and processes that address how
these changes will be implemented and communicated to the users.
An effective plan will provide a thorough review with the clinical
decision representatives to make certain all concerns and potential
issues are identified and that a clear process for resolving
those issues is in place. Include the following primary phases/activities
in the plan:
- Assessment – Create a list of all
currently active Ordersets and the proposed list of Ordersets
required for activation with the new HIS system. Identify current
and proposed processes for revising active Ordersets and adding
new Ordersets. Prepare a project plan that identifies key tasks,
personnel and the time needed to accomplish the project.
- Communication – This should be ongoing.
Share all information with individuals or groups who are involved
or use Ordersets; this will greatly reduce the chance of missing
key elements of the process. The significance and spirit of
the Orderset requires excellent, open communication among all
parties.
- Development Planning – Further develop
the project plan by adding detailed information and tasks. Assemble
key individuals and groups who will be involved in the project
and discuss their roles and responsibilities. Identify
and document the standards that will be used when designing
and building each Orderset. Create documents and templates
that will be needed to design, build, test, and communicate
each step of the project.
Identifying the complexity of the various Ordersets and separating
them into groups based upon complexity helps determine the timeline
and level of effort to complete the development of the Ordersets.
In some cases the use of a “trial” or test phase
to validate the amount of time and level of effort for each “class” of
Orderset will help you plan. Have a kickoff meeting with all
parties present. Review each step of the process and fully explain
how the primary tasks should occur and why each step is important.
You’ll find your resources are more likely to provide better
quality and energy if they understand the importance of the “why’s.”
- Design Phase – Create a paper or electronic
version of the requested Orderset (making sure to adhere by
the standards that were previously identified), and gain approval/signature
for the design. This should be done systematically by
facility, specialty, group, or individual based on the needs
of the organization. This systematic approach will allow for
the least amount of interruptions in the normal day-to-day
operations of the personnel that will be providing the design
specs and approvals.
There will be modifications to the requested Ordersets, so bear
that in mind when determining how to track the Ordersets and
their associated change requests. Using good change management
practices will save time, effort and, most likely, your sanity.
- Build – Build the approved design
on the new system. Remember to build these in the appropriate
Pathway and migrate them when they have been fully tested.
Some may argue that building them in the Production Pathway
is safe and better. Trust us when we say it is not wise to
build anything in your Production Pathway. This can cause numerous
issues within your new module/system that may never have been
considered or impact your other modules negatively. Remember
most systems today are integrated, enterprise solutions and
should be tested that way to ensure a smooth running solution.
- Testing – This is a two-step process.
The analyst who is building the Orderset on the system should
verify that the Orderset has been built to design specifications
and test to make sure the Orderset will process correctly (i.e.,
all orders are orderable at each facility that will utilize
the Orderset). Next, a clinician who will be utilizing the
Orderset should test to make sure the Orderset processes and
functions as intended (i.e., order/actions appear at the expected
time).
- Approval – Obtain final approvals
and signatures for the build from the appropriate committee,
group, or individual. It’s best to have signoffs at each
stage of the development process. This helps to ensure each
stage is on track and reduces the chance that the Ordersets
will have to be redeveloped. When clinical and business users
understand the system capabilities and participate throughout
the process, the better your results will be. Keep in mind
this system is for them—they need to feel involved and
be part of the new changes.
- Training – Provide an appropriate
amount of training on the functionality and process for entering,
discontinuing, or modifying the new Ordersets. Training should
actually begin during the Assessment or Development Planning
phase. This will help down the line, but more importantly,
it will enable the clinical representatives to make more knowledgeable
system and workflow decisions. While seeing demos are beneficial,
rolling up your sleeves and actually using the new Ordersets
makes a significant impact.
- Activation – Prior to activating the
Ordersets, communicate to all appropriate personnel specifically
which Ordersets will be available and on what date and time.
Keep in mind that the migrations from the Development Pathway
to the Production Pathways will need to be considered. Remember,
it’s never as simple as turning on a light switch.
Problems with Ordersets development initiatives usually begin
in the Assessment Phase, when clinicians and other essential
personnel are not familiar with the functionality and capabilities
of the new system. Communication and documentation are vital
for preventing misconceptions about the functionality of the
new system.
When you follow the above key steps to create a smooth transition
from your facility’s current Orderset functionality to
the new system’s functionality, you’re setting up
for success.
Efficient Report
Coding for Effective Use
When designing and developing custom reports, it is best to
step back from the detail to see how a few slight modifications
in design can open opportunities for the reuse of programs in
other areas of your organization. For example, consider
a request to produce a report that prints information for patients
with Multiple Sclerosis. By designing the report so the
Multiple Sclerosis code was an input parameter instead of hard
coded within the report, the organization can also produce a
report for the Cardiovascular Department that listed all heart
related problems. There is no need to worry about the user
having to enter the specific code for the report they need. By
using some creative screen building techniques the parameter
can be applied to the report behind the scenes.
Cost savings for developing reports that are parameter driven
not only save time and resources during initial development,
but will also keep long term cost down for report maintenance
and during system upgrades. The fewer custom reports you
have to maintain, track, and migrate, the better.
Create and use a Custom Reports Standards document that outlines
all the “must have” elements on each report. For
example, all reports must identify the source program name, be
able to process for one or all facilities, include totals whenever
applicable or have a page number in a certain location. Setting
standards early can improve support capabilities by making custom
reports easier to identify and locate.
Have you ever found a user pulling the same report 3, 5 or even
10 times in a row for different patients? Have you noticed
what that does for overall system performance? If the report
is driven by the entry of an account number, consider modifying
the report to print by user’s Hot List or Common List of
patients, such as those assigned to a nurse during his/her shift. This
allows the user to put the entire group of patients in one report
request, causing a single occurrence of the report to process
instead of one occurrence for each patient. Using this
coding method will greatly improve the efficiency of both the
report and overall system performance.
Tips on Building
Your RIS Exam Dictionary
While this article was written with GE’s Imagecast in
mind, it applies to most all RIS projects. When designing
Imagecast RIS, one of the most important aspects is preparing
and building your Exam dictionary. Every exam that can
be performed in an Imaging department is built as a specific
entry in the Exam dictionary. Most functions performed within
the system will reference the Exam dictionary at some point.
The Exam dictionary contains information relating to every diagnostic
test that is performed. Each entry includes billing codes,
duration, which room(s) the exam can be performed in, and many
other data elements which enable proper scheduling.
One of the most troublesome aspects of building the Exam dictionary
lies in the naming convention given to the exams. In Imagecast,
each exam is assigned a description as well as an exam code.
The codes and descriptions are used by all clinicians accessing
the system when searching for exams to schedule, arrive, or complete.
As the exam code section of the Imagecast exam dictionary is
limited to ten (10) characters and as each code must be unique,
the following recommendations should be followed in order to
make the search process easier for your end users:
- Begin each exam code with an abbreviation of the modality
for which it belongs. For example, an Ultrasound of the Carotid
Arteries could be given an exam code of USCAR - (US for Ultrasound,
CAR for Carotid).
- Abbreviate contrast information for exams. When building
CT Abdomen exams, this is an example of codes:

- Standardizing whenever possible will make codes easier to
maintain and simpler for schedulers to find. Here are some
examples:

- Avoid building exam codes with special characters such as
dashes or slashes. A user will have more difficulty searching
for an exam code of CT-ABD versus CTABD because they have to
enter the dash.
- Build the Exam dictionary in Excel or on paper BEFORE entering
into the actual dictionary. Make sure supervisors and
leads from each modality (CT, MRI, US, etc) have reviewed for
accuracy and signed off before actually loading the information
into the system. Exams that are found to be inaccurate
can be inactivated, but never deleted.
Approaching the build of the Exam dictionary requires a concerted
and organized effort. By spending additional time
on design to insure a consistent naming convention is used, by
completing the entire exam dictionary in Excel and by obtaining
validation from all Radiology departments you are headed towards
a successful implementation.
Good Planning is Key to Implement Ordersets
When implementing an Orderset within a new HIS system, correctly
meeting the needs and wants of your physicians, nurses and
other end users is key to success. It is often very difficult
to address existing and newly requested functionality, requirements,
and regulatory compliance while at the same time reducing
medical errors and addressing many other issues and concerns.
That’s why it’s important to thoroughly work
through and map out the entire process.
Utilizing experienced resources to plan, design, build, test,
and implement the new system is vital for getting the system
up and functioning within the allotted timeframe and budget
while at the same time gaining approval from the end users.
With a resource that provides the proper experience, information,
planning and foresight, you can avoid unwanted issues and problems.
The Plan
The plan needs to include adequate communication, design, approval,
testing, and training with the appropriate clinical representatives.
The representatives should thoroughly understand the new
capabilities and limitations of the system and whether or
not the new functionality will work seamlessly with the expected
workflow process. Your plan should also include processes
that accommodate new requests and requests for revisions,
and processes that address how these changes will be implemented
and communicated to the users.
An effective plan will provide a thorough review with the
clinical decision representatives to make certain all concerns
and potential issues are identified and that a clear process
for resolving those issues is in place. Include the following
primary phases/activities in the plan:
- Assessment – Create a
list of all currently active Ordersets and the proposed list
of Ordersets required for activation with the new HIS system.
Identify current and proposed processes for revising active
Ordersets and adding new Ordersets. Prepare a project plan
that identifies key tasks, personnel and the time needed
to accomplish the project.
- Communication – This
should be ongoing. Share all information with individuals or
groups who are involved or use Ordersets; this will greatly
reduce the chance of missing key elements of the process. The
significance and spirit of the Orderset requires excellent,
open communication among all parties.
- Development Planning – Further
develop the project plan by adding detailed information and
tasks. Assemble key individuals and groups who will be
involved in the project and discuss their roles and responsibilities. Identify
and document the standards that will be used when designing
and building each Orderset. Create documents and templates
that will be needed to design, build, test, and communicate
each step of the project.
Identifying the complexity of the
various Ordersets and separating them into groups
based upon complexity helps determine the timeline and level
of effort
to complete the development of the Ordersets. In some cases
the use of a “trial” or
test phase to validate the amount of time and level of effort
for each “class” of
Orderset will help you plan. Have a kickoff meeting with all parties
present. Review each step of the process and fully explain
how the primary
tasks should occur and why each step is important. You’ll
find your resources are
more likely to provide better quality and energy if they understand
the importance of the “why’s.”
Design Phase – Create
a paper or electronic version of the requested Orderset (making
sure to adhere by the standards that were previously identified),
and gain approval/signature for the design. This should
be done systematically by facility, specialty, group, or individual
based on the needs of the organization. This systematic approach
will allow for the least amount of interruptions in the normal
day-to-day operations of the personnel that will be providing
the design specs and approvals.
There will be modifications to the
requested Ordersets, so bear that in mind when
determining how to track the Ordersets and their associated
change requests.
Using good change management practices will save time, effort and,
most likely, your sanity.
Build – Build the approved
design on the new system. Remember to build these in the appropriate
Pathway and migrate them when they have been fully tested.
Some may argue that building them in the Production Pathway
is safe and better. Trust us when we say it is not wise to
build anything in your Production Pathway. This can cause numerous
issues within your new module/system that may never have been
considered or impact your other modules negatively. Remember
most systems today are integrated, enterprise solutions and
should be tested that way to ensure a smooth running solution.
Testing – This is a two-step
process. The analyst who is building the Orderset on the system
should verify that the Orderset has been built to design specifications
and test to make sure the Orderset will process correctly (i.e.,
all orders are orderable at each facility that will utilize
the Orderset). Next, a clinician who will be utilizing the
Orderset should test to make sure the Orderset processes and
functions as intended (i.e., order/actions appear at the expected
time).
Approval – Obtain final
approvals and signatures for the build from the appropriate
committee, group, or individual. It’s best to have signoffs
at each stage of the development process. This helps to ensure
each stage is on track and reduces the chance that the Ordersets
will have to be redeveloped. When clinical and business users
understand the system capabilities and participate throughout
the process, the better your results will be. Keep in mind
this system is for them—they need to feel involved and
be part of the new changes.
Training – Provide an
appropriate amount of training on the functionality and process
for entering, discontinuing, or modifying the new Ordersets.
Training should actually begin during the Assessment or Development
Planning phase. This will help down the line, but more importantly,
it will enable the clinical representatives to make more knowledgeable
system and workflow decisions. While seeing demos are beneficial,
rolling up your sleeves and actually using the new Ordersets
makes a significant impact.
Activation – Prior to
activating the Ordersets, communicate to all appropriate personnel
specifically which Ordersets will be available and on what
date and time. Keep in mind that the migrations from the Development
Pathway to the Production Pathways will need to be considered.
Remember, it’s never as simple as turning on a light
switch.
Problems with Ordersets development initiatives usually begin
in the Assessment Phase, when clinicians and other essential
personnel are not familiar with the functionality and capabilities
of the new system. Communication and documentation are vital
for preventing misconceptions about the functionality of the
new system.
When you follow the above key steps to create a smooth transition
from your facility’s current Orderset functionality to
the new system’s functionality, you’re setting
up for success.
Good Planning is Key to Implement Ordersets
When implementing an Orderset within a new HIS system, correctly
meeting the needs and wants of your physicians, nurses and
other end users is key to success. It is often very difficult
to address existing and newly requested functionality, requirements,
and regulatory compliance while at the same time reducing
medical errors and addressing many other issues and concerns.
That’s why it’s important to thoroughly work
through and map out the entire process.
Utilizing experienced resources to plan, design, build, test,
and implement the new system is vital for getting the system
up and functioning within the allotted timeframe and budget
while at the same time gaining approval from the end users.
With a resource that provides the proper experience, information,
planning and foresight, you can avoid unwanted issues and problems.
The Plan
The plan needs to include adequate communication, design, approval,
testing, and training with the appropriate clinical representatives.
The representatives should thoroughly understand the new
capabilities and limitations of the system and whether or
not the new functionality will work seamlessly with the expected
workflow process. Your plan should also include processes
that accommodate new requests and requests for revisions,
and processes that address how these changes will be implemented
and communicated to the users.
An effective plan will provide a thorough review with the
clinical decision representatives to make certain all concerns
and potential issues are identified and that a clear process
for resolving those issues is in place. Include the following
primary phases/activities in the plan:
- Assessment – Create a
list of all currently active Ordersets and the proposed list
of Ordersets required for activation with the new HIS system.
Identify current and proposed processes for revising active
Ordersets and adding new Ordersets. Prepare a project plan
that identifies key tasks, personnel and the time needed
to accomplish the project.
- Communication – This
should be ongoing. Share all information with individuals or
groups who are involved or use Ordersets; this will greatly
reduce the chance of missing key elements of the process. The
significance and spirit of the Orderset requires excellent,
open communication among all parties.
- Development Planning – Further
develop the project plan by adding detailed information and
tasks. Assemble key individuals and groups who will be
involved in the project and discuss their roles and responsibilities. Identify
and document the standards that will be used when designing
and building each Orderset. Create documents and templates
that will be needed to design, build, test, and communicate
each step of the project.
Identifying the complexity of the
various Ordersets and separating them into groups
based upon complexity helps determine the timeline and level
of effort
to complete the development of the Ordersets. In some cases
the use of a “trial” or
test phase to validate the amount of time and level of effort
for each “class” of
Orderset will help you plan. Have a kickoff meeting with all parties
present. Review each step of the process and fully explain
how the primary
tasks should occur and why each step is important. You’ll
find your resources are
more likely to provide better quality and energy if they understand
the importance of the “why’s.”
Design Phase – Create
a paper or electronic version of the requested Orderset (making
sure to adhere by the standards that were previously identified),
and gain approval/signature for the design. This should
be done systematically by facility, specialty, group, or individual
based on the needs of the organization. This systematic approach
will allow for the least amount of interruptions in the normal
day-to-day operations of the personnel that will be providing
the design specs and approvals.
There will be modifications to the
requested Ordersets, so bear that in mind when
determining how to track the Ordersets and their associated
change requests.
Using good change management practices will save time, effort and,
most likely, your sanity.
Build – Build the approved
design on the new system. Remember to build these in the appropriate
Pathway and migrate them when they have been fully tested.
Some may argue that building them in the Production Pathway
is safe and better. Trust us when we say it is not wise to
build anything in your Production Pathway. This can cause numerous
issues within your new module/system that may never have been
considered or impact your other modules negatively. Remember
most systems today are integrated, enterprise solutions and
should be tested that way to ensure a smooth running solution.
Testing – This is a two-step
process. The analyst who is building the Orderset on the system
should verify that the Orderset has been built to design specifications
and test to make sure the Orderset will process correctly (i.e.,
all orders are orderable at each facility that will utilize
the Orderset). Next, a clinician who will be utilizing the
Orderset should test to make sure the Orderset processes and
functions as intended (i.e., order/actions appear at the expected
time).
Approval – Obtain final
approvals and signatures for the build from the appropriate
committee, group, or individual. It’s best to have signoffs
at each stage of the development process. This helps to ensure
each stage is on track and reduces the chance that the Ordersets
will have to be redeveloped. When clinical and business users
understand the system capabilities and participate throughout
the process, the better your results will be. Keep in mind
this system is for them—they need to feel involved and
be part of the new changes.
Training – Provide an
appropriate amount of training on the functionality and process
for entering, discontinuing, or modifying the new Ordersets.
Training should actually begin during the Assessment or Development
Planning phase. This will help down the line, but more importantly,
it will enable the clinical representatives to make more knowledgeable
system and workflow decisions. While seeing demos are beneficial,
rolling up your sleeves and actually using the new Ordersets
makes a significant impact.
Activation – Prior to
activating the Ordersets, communicate to all appropriate personnel
specifically which Ordersets will be available and on what
date and time. Keep in mind that the migrations from the Development
Pathway to the Production Pathways will need to be considered.
Remember, it’s never as simple as turning on a light
switch.
Problems with Ordersets development initiatives usually begin
in the Assessment Phase, when clinicians and other essential
personnel are not familiar with the functionality and capabilities
of the new system. Communication and documentation are vital
for preventing misconceptions about the functionality of the
new system.
When you follow the above key steps to create a smooth transition
from your facility’s current Orderset functionality to
the new system’s functionality, you’re setting
up for success.
If you would like additional information regarding this
article please send an email to Business.Services@Atlanticon.net requesting
a copy of “Good Planning is Key to Implement
Ordersets”.
Overcoming the Vendor Honeymoon —Taking Control of Your Project
When a hospital embarks on a large project to install one of
the common HIS systems, the demo is still fresh in everyone’s
mind. A visual image of a smoothly run project with a vendor
dedicated solely to you is the expectation that most teams have. There
is an air of excitement as you await the kickoff, knowing that
you will be guided every step of the way. You’re
on your honeymoon! Within a few months, you realize that
the project plan doesn’t really list all your tasks, learning
the new system is not as simple as you had hoped, redesigning
workflows is difficult because you’re not confident of
what to expect, issues seem to be on the rise – more questions
than answers, and the vendor is busy with 3 other clients! Honeymoon…officially
over!
During many of the hospital IT projects in which we’ve
been involved, we notice that the hospital team does indeed have
a tendency to rely quite heavily on the vendor. When a
hospital believes that the vendor will take charge of the entire
project, it can sometimes set unrealistic expectations. When
Atlanticon is hired to help with the installation of a new system,
one of the first things we attempt to do is ascertain whether
the hospital’s project team consists of veterans or rookies. We
do this for a lot of reasons, but one of them happens to be the
topic of this article. We like to help hospital project
team members gain a realistic expectation of what duties belong
to them versus what they should reasonably expect of their vendor. By
taking control of your project early, you increase your chance
for a very successful installation!
Typically, a project veteran (one who has dealt with more than
3 system installs) understands the limits of their software vendor,
and more importantly, understands what tasks will fall to the
hospital team. Rookies, on the other hand, experience what
we call the “Vendor Honeymoon” phase – something
we’ve all lived through and certainly nothing to be ashamed
of.
Sooner or later, the hospital team realizes that the project
belongs to them and the success of the project lies on their
own shoulders. This is the point at which we notice the
project taking a very positive turn. Vendors know their
own systems, but they don’t know your hospital. Vendors
are very aware of how their system works out of the box, but
they may not have all the answers once the system is tailored
to your needs.
Here are some of the more common areas of a project where the
hospital team should take early ownership:
- Project Plan – a vendor will provide a plan that covers
their tasks and some of yours. You need to actively include
all tasks that are the hospital’s responsibility. Don’t
forget tasks surrounding downtime planning, change management,
operations and infrastructure tasks, hardware acquisition and
installation, forms changes, policy revisions, and activation
planning. And keep in mind that you will not remember
to include every task initially – prepare to continue
updating the plan with additional tasks and reminders as each
new phase is beginning.
- Scope – the vendor will identify the scope of what
you purchased and the scope of their services, but only you
know how you intend to utilize your purchases. For example,
you may purchase the Order Entry module. The vendor will
not know that you intend to utilize it for order entry to 29
departments and that 17 of those will receive printed requisitions
and 12 will generate charges upon order. Take control
of detailing the scope.
- Issues – the vendor will have an interest in tracking
the issues that they need to fix. However, they should
not be responsible for all the issues that are hospital specific. You
should implement your own issue tracking system and be diligent
about logging every issue and key decision.
- Testing – the vendor can help resolve issues found
during testing, but typically can’t prepare your test
scripts. Most hospitals heavily tailor the system, and
by the time testing arrives you are the expert in how the system
should work at your organization, i.e., you are responsible
for creating your own test scripts, preparing the logistics
of the test room, running the test phase, and logging the issues
that arise.
- Activation Planning – the vendor will be prepared to
be on-site, help with conversions and cutover planning, but
for the most part, activation planning belongs to you. You
will need to determine where your command center will be located,
how to set it up with equipment, develop a support schedule,
and create a step-by-step activation plan.
These are just a few examples of areas where responsibility
should be clearly understood. We hope that this small list
can guide your team into an early realization that the project
belongs to you. Face it and embrace it!
As always, we would certainly enjoy speaking with you about
your own experiences with this topic. Good luck in your
next project!
Project Work Area – Sitting
Together, Succeeding Together
How many times have you been involved in a large project where
you feel as if your teams are working in silos? Well intentioned
project members work diligently on their assignments – teams
for pharmacy, orders, registration, and clinical documentation,
all work hard to design and build – yet they seem to lack
the confidence that they are building an integrated system that
makes sense and works seamlessly. That’s because
integrated systems require integrated design, integrated tailoring,
and integrated testing. And how do you get at? By
incorporating integrated seating!
Whenever a hospital undertakes a large implementation project,
Atlanticon suggests the creation of a common work area to insure
you deliver an integrated system. Projects suffer from
communication issues all the time, and a good Project Manager
will step in to encourage good communication and even install
methods and tools to help the right hand be aware of the left
hand’s activities. But there is no better way to
accomplish a cohesive work team than to designate a common work
area and require your teams to perform key tasks together. They
synergy that is created by working in a common area is unbelievable. Teams
feed off one another, they learn how each team is progressing,
and the result is a more integrated system.
Expect some pushback and be prepared to deal with it. First,
everyone has their own office / cubicle and doesn’t like
to leave it. Second, designating a common area may not
be easily feasible in your organization. And third, it
may seem difficult to coordinate. But you need to overcome
those obstacles, as there is a big payoff to having your teams
spend time together daily.
Atlanticon recommends the following for all large projects:
- Establish / reserve a room large enough to house the IT members
from each of your key application teams, as well as some additional
spaces for invited guests (liaisons, interface, or conversion
staff for example.)
- This room will probably be used ultimately for testing, training,
and maybe even your activation command center.
- Designate a time each day (8 am – 12 pm or 1 pm – 4
pm) for your team to collect there so schedules can be built
around that time. Require your key application teams,
Pharmacy, Orders, Clin Doc, HIM, Registration, CPOE, etc.,
to plan on working on their project related tasks in that room.
- Enforcing the use of the Project Work Area for the design
and build phases make the most sense, as these are phases of
the project where it’s essential that the teams develop
an integrated project.
- Your PM should drive this cohesive approach, and encourage
/ schedule “show me” sessions – allowing
each team an opportunity to present what they are doing with
design or demo portions of their build to insure that other
teams can ask questions, compare, and most importantly, be
confident that they are creating a system that will work together
FOR the user community.
While most sites have initially been reluctant to enforce Project
Work Areas, every single one has been very pleased with the outcome. All
of us are inherently resistant to change – and we’re
uncomfortable giving up our ‘turf.’ But project
teams need to look at the bigger picture and recognize the value
of this minor, yet important, approach. Very recently,
one former client from Virginia called to say, “We hated
it when you made us do it, but it turned out to be the best thing
for this project and for our users!” They now designate
Project Work Areas for all their projects.
Call Today & Start the Conversation
Our team of healthcare system installation professionals have the experience
you demand to help you with any phase of your project — from
vendor selection through final audit. Contact
us today.
|